TRACK PROGRESS

Project Timeline

2017
Nov 2017

Finalize Term Sheet for Preferred Site

Nov 2017

General Contractor Selection

Oshkosh Corporation selected Miron Construction as the General Contractor for our new Global Headquarters.

Dec 2017

Land Sale Approved

The purchase of 32 acres of land from the City of Oshkosh was approved.

2018
Jan 2018

Schematic Design Approved

May 2018

Design Development and Construction Documents Delivered

May 2018

Ground Breaking

Aug 2018

Sitework and Foundations Complete

2019
May 2019

Core and Shell Complete

Sep 2019

Building Interior Completed

Interior improvements and installation of furniture, fixtures and equipment

Oct 2019

Occupancy

Team Members from Oshkosh Corporation begin working at the new Global Headquarters.